Skip to content

Five Valleys Site Update

Five Valleys Site Update

15 Jul 2019

Site Update Week Commencing 15th July

Work on the Five Valleys development is progressing well and all the businesses in the centre remain open and trading.

Speller Metcalfe are also working on the Phase 3 works on the project and this week they will be continuing demolition to units 5-9 as well as the asbestos removal. This week the contractors will also commence the demolition to units 12-15. 

This week there are also converting the Bramley’s unit into a permanent Speller Metcalfe office space. The team are also preparing the service yard area and they are preparing for the piling which is to commence in the next couple of weeks. 

Work is also progressing well on the first floor apartments above the Kings Street units which is being undertaken by Ardent. As well as this Barnwood Construction are completing their phase of work to the King Street retail units and this elevation to the centre.